Prime Minister Balen Shah and his Indian counterpart Narendra Modi have jointly laid the foundation stone for the 669-megawatt Lower Arun Hydropower Project.
Following their bilateral meeting in New Delhi on Monday, the two prime ministers laid the foundation stone for the project, which will be constructed in Koshi Province.
The project, estimated to cost approximately USD 600 million, will be constructed by a company under India's state-owned Satluj Jal Vidyut Nigam (SJVN).
The project's financing arrangements have been completed, and it has now entered the construction phase.
The project development agreement (PDA) for the project, located in Sankhuwasabha and Bhojpur districts, was signed between the Investment Board Nepal and SJVN Lower Arun Power Development Company on June 1, 2023.
The agreement was signed during the India visit of then-prime minister Pushpa Kamal Dahal.
According to sources at the Investment Board, Nepal will receive 21.9 percent of the total electricity generated by the project free of cost. In addition, Nepal will receive royalties and other financial benefits in accordance with prevailing regulations.
The project will be developed under the Build, Own, Operate, and Transfer (BOOT) model. It must be handed over to the Government of Nepal in operational condition after 25 years of commercial operation.
One of the distinctive features of the Lower Arun project is that it does not require the construction of a separate large dam. Instead, it will utilize water discharged after electricity generation at the 900 MW Arun III Hydropower Project, which is currently under construction.
A tunnel approximately 17 kilometers long will be constructed to channel the water to the powerhouse. The project will have four generating units, each with a capacity of 167.25 MW.
According to the company, the project is expected to generate approximately 2.9 billion units of electricity annually once completed.
In April 2023, the Investment Board Nepal approved foreign investment worth Rs 92.68 billion for the project.
SJVN was awarded responsibility for developing the project in 2021. At the time, the proposed capacity was 679 MW, which was subsequently revised to 669 MW.
SJVN is also developing the 900 MW Arun III Hydropower Project on the same river.
With the groundbreaking of Lower Arun, the combined installed capacity of the two major hydropower projects being developed by the Indian state-owned company on the Arun River has reached 1,569 MW.